Updating a Project
Top  Previous  Next

By updating you project, Timeless Time & Expense can keep your task hierarchy up to date with your project. Your project time and costs and even estimates can be updated in your project plan provided your project management software and project options support it.

The estimate of Database Design task is going to take more time that we initially thought. Update the time estimate to 30 hours on the task's properties. Now update the project

Select Projects from the Tools menu to display the Projects dialog. Highlight the SuperSaverPlan project. Press the Update button. Select only the Update Work Estimates item. Press OK.